Stages of building the Home THAT PUTS PEOPLE BACK ON THEIR FEET

What’s already behind us?

STAGE 1: Property purchase + preparatory work

In the first stage, thanks to donations from our benefactors, we raised 100% of the necessary funds

Thanks to donations from our supporters, we have raised 661 329 PLN

100%

The scope of stage 1 included:

1. Purchase of real estate – a plot of land with a terraced house standing on it

The purchase was finalised by a notarial deed

Thanks to donations from our supporters, we have raised
383 413 PLN

100%

View gallery

2. Preparation of technical documentation

The necessary surveying and geological studies were carried out and architectural designs were prepared. A permit for the renovation and extension of the building was obtained.

Thanks to donations from our supporters, we have raised
28 297 PLN

100%

View gallery

3. Construction of a ramp necessary for the execution of construction works

A ramp was constructed from steel obtained from Arcelor Mittal, allowing construction works to be carried out.

Thanks to donations from our supporters, we have raised
9 840 PLN

100%

View gallery

4. Construction work

Comprehensive construction work has begun, including:

  • concreting the foundations on a section constituting ⅓ of the total length of the reinforcement work,
  • removing all plaster,
  • demolishing the ceilings in the basements.

Thanks to donations from our supporters, we have raised
221 329 PLN

100%

View gallery

5. 5. Development of industry-specific projects

Comprehensive installation designs were developed, including:

  • structural design,
    water and sewage systems,
  • central heating,
  • electrical installations,
  • ventilation and air conditioning.

Thanks to donations from our supporters, we have raised
18 450 PLN

100%

View gallery

6. Material support from construction companies

The project received significant material support from industry partners:

  • TLC Rental – donation of construction fencing,
  • Wienerberger – donation of ceramic construction blocks,
  • Arcelor Mittal – donation of steel.

Value of in-kind support

137 400 PLN

View gallery

STAGE 2: Creation of places supporting pro-health activities

In the second stage, thanks to the support of donors, volunteers and funding, two important elements of the project were created:

1. Active Hydrogen Studio offering molecular hydrogen inhalations.

  • co-financing from the State Fund for Rehabilitation of Disabled Persons (PFRON) and the Social Economy Support Centre (OWES)
  • material support from companies:
    • King Klinker S.A. – clinker bricks for the façade
    • FUH GROMOTKA – wall slats and doors
  • voluntary services provided by the following companies:
    • Skolbud – renovation and construction works
    • MAŁECCY design office – architectural design

Value of support 320 359 PLN

View gallery

2. Therapeutic garden

A garden has been created next to the foundation’s headquarters, providing a relaxation and recreation area for our charges. Therapeutic workshops and physical activities are also held in the garden.

  • material support from the company: Trawnik Producent Arkadiusz Gumieniczuk
  • support from volunteers in carrying out the work

Value of support 320 359 PLN

View gallery

What lies ahead?

STAGE 3: Open shell

In the third stage of the project, we are raising funds to bring the building to a shell condition.

What remains to be done:

1. Securing works and reinforcement of foundations

Thanks to donations from our supporters, we have raised
0 PLN out of 420 000 PLN

0%

2. Bricklaying and wall reinforcement

Thanks to donations from our supporters, we have raised
0 PLN out of 330 000 PLN

0%

3. Construction of roof trusses and roofing

Thanks to donations from our supporters, we have raised
0 PLN out of 270 000 PLN

0%

4. Replacement of ceilings between floors

Thanks to donations from our supporters, we have raised
0 PLN out of 680 000 PLN

0%